Emulex ONECONNECT OCE10102-F Guia de Instalação Página 8

  • Descarregar
  • Adicionar aos meus manuais
  • Imprimir
  • Página
    / 13
  • Índice
  • MARCADORES
  • Avaliado. / 5. Com base em avaliações de clientes
Vista de página 7
Fujitsu OneConnect OCe10102 CNA Installation Manual - Hardware Page 8
Applying Power
To apply power:
1. Verify that the CNA is securely installed in the computer.
2. Verify that the correct media is attached.
3. Plug in and turn on the computer.
4. Observe the boot banner for Power On Self Test (POST) results.
Viewing the LEDs
Green and amber LEDs can be seen through openings in the CNA's mounting bracket. Each
corresponding LED is summarized below:
Activity: (Green) (Ethernet Link)
Blink = Activity
Off = No activity
Link (Amber)
On (constantly) = Link up
OFF = Link down
Figure 5: CNA LED Indicators
Vista de página 7
1 2 3 4 5 6 7 8 9 10 11 12 13

Comentários a estes Manuais

Sem comentários